July 26, 2011

Geothermal Clean Energy Investment project for Indonesia approved

With about 27,000 MW of geothermal power potential, Indonesia has roughly 40% of the world's resources. However, as of 2011, only 4% of the country's total geothermal resources have been developed to produce power. The $574.70 million Geothermal Clean Energy Investment Project, of which the World Bank Group is contributing $175 million, will finance the construction of the Steamfield Above-Ground System (SAGS) and the Ulubelu and Lahendong (Tompaso) geothermal fields.

Resource Gallery

Geothermal Clean Energy Investment Project: Project Appraisal Document

Document date: June 27, 2011
The document presents contextual and project information needed to approve the project.

Geothermal Clean Energy Investment Project

P113078: Approved July 26, 2011
The project profile contains an overview of the project, financial details, and a list of project documents related to the project.

Geothermal Resource Risk in Indonesia: A Statistical Inquiry

Document date: July 15, 2014
The paper presents a statistical study of the geothermal resource risk in Indonesia, specifically concerning the resource base, well productivity, and drilling costs per well.